What is an ICRA?

An Infection Control Risk Assessment (ICRA) is a documented assessment, made before construction or renovation in a healthcare facility, of how the work could spread dust, mold spores and other contaminants to patients, and which precautions will prevent it. The facility’s infection prevention team leads it with facilities staff and the contractor. Accrediting bodies and the FGI Guidelines for the design and construction of healthcare facilities expect one before work starts.

What are the construction activity types?

TypeDescriptionExamples
AInspection and non-invasive activitiesRemoving a ceiling tile for visual inspection, painting without sanding, minor electrical trim
BSmall-scale, short-duration work that creates minimal dustRunning cable, accessing chase spaces, cutting walls or ceilings where dust can be controlled
CWork that generates moderate to high dust or removes fixed building componentsSanding walls, removing flooring or casework, building new walls, work that cannot finish in one shift
DMajor demolition and constructionHeavy demolition, removing complete cabling systems, new construction over consecutive shifts

What are the patient risk groups?

  • Low: office and non-patient areas.
  • Medium: areas such as cardiology, endoscopy, nuclear medicine, physical therapy, radiology and respiratory therapy.
  • High: areas such as the emergency department, labor and delivery, laboratories, newborn nursery, outpatient surgery, pediatrics, pharmacy and post-anesthesia care.
  • Highest: areas caring for immunocompromised patients, such as burn units, cardiac catheterization, central sterile supply, intensive care, oncology, negative-pressure isolation rooms and operating rooms.

The facility decides which group each area belongs to; these lists are typical examples, not rules.

How is the ICRA class determined?

The class is read from a matrix that crosses the activity type with the patient risk group:

Patient risk groupType AType BType CType D
LowIIIIIIII/IV
MediumIIIIIIIV
HighIIIIII/IVIV
HighestIIIII/IVIII/IVIV

This is the classic matrix most facilities have used for years. The American Society for Health Care Engineering (ASHE) has since published an updated framework, ICRA 2.0, and some facilities now use it. Always follow the version and the class your facility assigns.

What precautions does each class require?

  • Class I: work done by methods that keep dust to a minimum; ceiling tiles replaced promptly after inspection.
  • Class II: active dust control such as water mist, sealed unused doors and vents, covered waste containers and wet-wiped surfaces.
  • Class III: the HVAC to the work area isolated; critical barriers completed to seal the area before work begins; negative air pressure maintained with HEPA-filtered units; waste moved in covered carts.
  • Class IV: everything in Class III, plus sealed penetrations, an anteroom that all personnel pass through, and protective clothing or HEPA vacuuming before leaving the work area.

What does the class mean for temporary walls?

Classes I and II often need no full barrier at all. Classes III and IV need a floor-to-ceiling critical barrier sealed at its joints, top and bottom, with a controlled door, and Class IV adds an anteroom. RX Wall Systems plans healthcare containment to the class and written requirements your facility sets, coordinated with the negative-air equipment your contractor provides. Send the ICRA permit with your quote request.